Planning and Estimating Production Rates
/ Description | Slow | Ave | Fast | Units |
Dozer, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile | 13.9 | 20.4 | 25.0 | m3/hr |
Dozer, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile | 7.6 | 9.5 | 12.6 | m3/hr |
Dozer, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile | 14.2 | 20.4 | 25.6 | m3/hr |
Dozer, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile | 7.6 | 10.2 | 12.8 | m3/hr |
Dozer, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile | 12.7 | 18.4 | 23.2 | m3/hr |
Dozer, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile | 6.9 | 8.9 | 11.6 | m3/hr |
Dozer, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile | 11.6 | 16.9 | 21.3 | m3/hr |
Dozer, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile | 6.3 | 8.2 | 10.4 | m3/hr |
Dozer, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile | 23.8 | 28.5 | 35.7 | m3/hr |
Dozer, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile | 16.7 | 18.5 | 20.4 | m3/hr |
Dozer, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile | 25.0 | 32.0 | 37.0 | m3/hr |
Dozer, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile | 17.2 | 19.3 | 21.2 | m3/hr |
Dozer, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile | 21.7 | 27.5 | 33.3 | m3/hr |
Dozer, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile | 15.1 | 16.9 | 18.8 | m3/hr |
Dozer, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile | 19.6 | 24.5 | 30.3 | m3/hr |
Dozer, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile | 13.7 | 15.9 | 17.5 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Sand/Soil | 18.6 | 28.5 | 38.5 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Sand/Soil | 24.4 | 37.2 | 50.0 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Gravel | 18.9 | 28.6 | 38.4 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Gravel | 24.2 | 37.2 | 50.0 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Hardcore | 15.8 | 23.5 | 31.2 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Hardcore | 19.2 | 29.6 | 40.0 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Boulder Clay | 17.2 | 26.4 | 35.7 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Boulder Clay | 22.2 | 33.8 | 45.4 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Sand/Soil | 43.5 | 48.0 | 52.6 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Sand/Soil | 55.5 | 61.1 | 66.7 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Gravel | 43.8 | 48.3 | 52.9 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Gravel | 55.5 | 61.1 | 66.7 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Hardcore | 37.1 | 40.3 | 43.5 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Hardcore | 47.6 | 51.6 | 55.6 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Boulder Clay | 43.8 | 45.7 | 47.6 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Boulder Clay | 55.6 | 59.1 | 62.5 | m3/hr |