Pre-Drilling - Site Investigation

Type of Strata Plant Used  Rate (m/hr)
Top soft deposits of site fill Percussive / Rotary 10.00
Grade V/IV rock deposits Wash Boring 3.15
  Triple Tube Sampling 0.75
Grade III/II rock deposits Rotary 0.50
  Triple Tube Sampling 0.50

 

With a standard rig, working a 12 hour shift, a typical output rate of 66 hrs/hole/rig is possible. 

  1. Average depth of 61.15 m, total depth of 428 m
  2. Average rock socket depth of 4.65 m
  3. The durations ranged from 4 to 8 days
  4. Average of 5.85 days, total duration of 41 days.

The Target Founding level

Setting Out

 

 Before starting excavation at the pile position the following steps are taken:

 

Pile Tolerances

Pile Excavation / Casings

Calculation Of Bored Pile Construction / Excavation Time

 Operation

Element 

Details 

Hours 

Add or Remove

Reverse Circluation Drill Plant (RCD)

incl drill bit

2 hrs

Add or Remove

RCD drill bit

(incl assembly of drill string)

5 hrs

 

RCD bell-out bit

(incl drill string & stabilisers)

5 hrs

Installation

Airlift tremmie tube

 

5 hrs

 

Reinforcement cages

(time for joining each cage)

2 hrs

Cleaning Time

Initial airlift cleaning

(after finishing excavation)

8 hrs

 

Final airlift cleaning

(after fixing steel cage)

2 hrs

Concreting

Incl extract casing

( < 70  m deep)           

12 hrs

 

 

( > 70 and < 95  m deep)

14 hrs

 

 

( > 95 and < 135 m deep)

48 hrs

Curing Time

Only required prior to removal of telescopic casings

 

72 hrs

Cycle Time

Move piling setup to next location

 

2 hrs

 

 

 

 

Shaft Excavation

Strata

Plant Used              

Rate (m/hr)

 

General Fill (upper ground levels)

Grab

3.50 m/hr

 

Sand, Minor Rubble

Grab

2.10 m/hr

 

Marine / Alluvium Deposits

Grab

2.50 m/hr

 

CDG < 150

RCD/Grab

1.50 m/hr

 

CDG > 150 < 200

RCD

1.00 m/hr

 

CDG > 200, Compacted Gravel

RCD

0.50 m/hr

 

CDT

RCD / Grab

0.50 m/hr

 

Corestones

RCD / Chisel

0.50 m/hr

 

Rock Socket - Grade IV/V

RCD

0.25 m/hr

 

Rock Socket - Grade II/III

RCD

0.125 m/hr

 

Rock Socket - (Tendering Rate)

RCD

0.10 m/hr

Example - For a pile founding on rock at 60 m deep...

 (a) Calculate Allowance For Plant Time / Other Elements (hrs)....
 

Element Hours

Set up RCD

5.0

Excavate Time

See Below

Remove RCD (including drill bit, string and stabilisers)

5.0

Setup / Remove Airlift Tremmie Tube

5.0

Initial Post-Excavation Airlifting

5.0

Place reinforcement (5 No cages @ 12m = 5 x 2 hrs)

10.0

Setup / Remove Airlift Tremmie Tube

5.0

Final Post-Reinforcement Airlifting

2.0

Concrete and remove casing

12.0

Move to next location

2.0

Calculate Total Construction / Plant Time

52.0 hrs

(b) Calculate Allowance For Excavation Time (hrs)...
 

Depth of Strata (m)

Type of Rock

Production Rate (m/hr)

Plant Used

Time (Hrs)

0 - 20

Sand/minor rubble

2.00

Grab

10.0

20 - 35

CDG less than 150

1.50

RCD/Grab

10.0

35 - 47

CDG more than 150

1.00

RCD

12.0

47 - 57

CDG > 200/corestones           

0.50

RCD

20.0

57 - 60

Rock socket

0.20

RCD

15.0

 (c) Calculate Total Pile Excavation Time = 67.0 hrs

 (d) Overall Pile Time       

Description

Calculation

Hours

Construction / Plant Time

(“b” above)

52.0 hrs

Excavation Time

(“d” above)

67.0 hrs

OVERALL CYCLE TIME

(“b” + “d”)

119 hrs

(With 12 hr shifts)

(“b” + “d”)

9.9 days


 

 Bored Pile Construction As-Builts

Description

Rule of Thumb Pile Times (days)

Depth (m) =>

<20

<40

<70

<90

<135

Days Per Pile

4.0*

8.0

10.0

25.0

45.0

Note - due to the required plant assembly and operation times, 4 days is the minimum possible pile construction time for any situation.

Methods For Overcoming Obstructions

Element Hours
Remove RCD 5 hrs
Install Tremie Concrete Tube 5 hrs
Place Concrete Plug 2 hrs
Cure Concrete 36 hrs
Replace RCD and drill string 5 hrs
TOTAL TIME LOSS 53 hrs (2.2 days or 4.4 shifts)

Cleaning of Pile Base

Reinforcement Cages

Description Duration
Fabricate 1 cage 2.5 hrs
Total cages required 5 no
Overall Fabrication Time 12.5 hours

Steel Stanchion Fabrication and Installation

Concreting

Sequence Of Piling

 Pile Testing