| Timber Studding |
5.9 |
6.2 |
6.8 |
m/hr |
| Metalwork System (MF) Studding |
1.6 |
2.0 |
2.5 |
m2/hr |
| Tape, Joint Sand and Top Coat Plasterboard |
1.1 |
1.5 |
2.1 |
m2/hr |
| Skimming to Plasterboards |
5.5 |
6.1 |
6.7 |
m2/hr |
| 5mm Hardboard Paneling, excluding studding time |
- |
3.2 |
3.6 |
m2/hr |
| 100mm Pine Paneling, excluding studding time |
0.8 |
1.1 |
1.4 |
m2/hr |
| Quality Hardwood Paneling, excluding studding time |
0.3 |
0.5 |
0.6 |
m2/hr |
| Fix 50mm Rocksil Insulation to cavities |
- |
17.8 |
20.2 |
m2/hr |
| Fix Timber Studding and Paramount Partitions |
2.6 |
3.0 |
3.4 |
m2/hr |
| Fix Timber Studding and Demountable Partitions |
0.8 |
1.1 |
1.6 |
m2/hr |
| Fix Timber Studding and Hills Duraboard Partitions |
3.0 |
3.5 |
3.9 |
m2/hr |
| Fix Timber Studding and Gyproc Laminated Partitions |
2.2 |
2.6 |
2.9 |
m2/hr |
| Stud Partitions, Butt Jointed, nailed |
5.9 |
7.3 |
9.1 |
m/hr |
| Stud Partitions, Butt Jointed, screwed |
3.5 |
4.6 |
5.8 |
m/hr |
| Stud Partitions, T&G Jointed, nailed |
2.9 |
3.6 |
4.8 |
m/hr |
| Stud Partitions, T&G Jointed, screwed |
2.1 |
2.8 |
3.7 |
m/hr |
| Stud Partitions, Fix Sole Plates |
- |
11.1 |
- |
m/hr |
| Stud Partitions, Fix Noggins |
- |
16.6 |
- |
m/hr |
| Stud Partitions, Drill 25-40mm Holes |
- |
28.5 |
- |
no/hr |
| Fix Toilet Partition System, Separation panels |
- |
0.8 |
- |
hrs/no |
| Fix Toilet Partition System, Wall Front Panels |
- |
0.7 |
- |
hrs/no |
| Fix Toilet Partition System, Separation Front Panels |
- |
0.6 |
- |
hrs/no |
| Fix Toilet Partition System, End Front Panels |
- |
0.6 |
- |
hrs/no |
| Fix Toilet Partition System, Hang Door to Panel |
- |
0.4 |
- |
hrs/no |
| Fix Toilet Partition System, Hand Door plugged to wall |
- |
0.6 |
- |
hrs/no |
| Fix Toilet Partition System, Fix Head Rails |
- |
0.1 |
- |
hrs/no |