Restoration Works
Planning Production Rates
| Task / Description | Slow | Ave | Fast | Units |
| Façade Cleaning, Water Jetting - Water Blasting | - | 25.0 | - | m2/day |
| Façade Cleaning, Acid Etching | - | 9.0 | - | m2/day |
| Façade Cleaning, Grit Blasting | - | 12.0 | - | m2/day |
| Cladding Restoration, Brickwork | - | 6.5 | - | m2/day |
| Cladding Restoration, Stonework courses | - | 20.0 | - | m/day |
