Tower Cranes

Planning Production Rates

Assembly & Disassembly
Task / DescriptionSlowAveFast
Erect and Setup 50m Gib11.0 days7.5 days
Dismantle 50m Gib10.0 days
Lifting Operations
Task / DescriptionSlowAveFast
Reinforcement Bins & Cages – First 15m Lift3.2 mins/lift
Reinforcement Bins & Cages – Above First 15m0.5 mins/15m - 0.5 mins/49.21ft
Crane Tracking Time3.3 seconds/m - 1.01 seconds/ft