Sewer and Stormwater Drains - Constants include laying, jointing and testing, but exclude excavation and backfilling

Earthenware Pipe – Rubber Ring Joints
DescriptionItemTradesman HoursLabourer Hours
Sewer(100mm – 4 in dia)0.50 mhr/m – 0.15 mhr/ft
(150mm – 6 in dia)0.70 mhr/m – 0.21 mhr/ft
(225mm – 9 in dia)1.00 mhr/m – 0.30 mhr/ft
Stormwater(100mm – 4 in dia)0.20 mhr/m – 0.06 mhr/ft
(150mm – 6 in dia)0.37 mhr/m – 0.11 mhr/ft
(225mm – 9 in dia)0.50 mhr/m – 0.15 mhr/ft
Bends, Junctions(100mm – 4 in dia)0.25 mhr/No – 0.25 mhr/No
(150mm – 6 in dia)0.25 mhr/No – 0.25 mhr/No
(225mm – 9 in dia)0.50 mhr/No – 0.50 mhr/No
PVC Pipe – Solvent Welded Joints
DescriptionItemTradesman HoursLabourer Hours
Sewer(100mm – 4 in dia)0.25 mhr/m – 0.08 mhr/ft
(150mm – 6 in dia)0.60 mhr/m – 0.18 mhr/ft
Stormwater(100mm – 4 in dia)0.20 mhr/m – 0.06 mhr/ft
(150mm – 6 in dia)0.35 mhr/m – 0.11 mhr/ft
Bends, Junctions(100mm – 4 in dia)0.25 mhr/No – 0.25 mhr/No
(150mm – 6 in dia)0.30 mhr/No – 0.30 mhr/No
Concrete Pipe – Rubber Ring Joints
DescriptionTradesman HoursLabourer Hours
(100mm – 4 in dia)0.35 mhr/m – 0.11 mhr/ft
(150mm – 6 in dia)0.43 mhr/m – 0.13 mhr/ft
(225mm – 9 in dia)0.50 mhr/m – 0.15 mhr/ft
(300mm – 12 in dia)0.65 mhr/m – 0.20 mhr/ft

Planning and Estimating Production Rates for Manholes and Gulleys

Precast Manhole Units

Concrete Pre-Cast Manhole Units

Task / DescriptionSlowAveFast
610 x 455 x 51 mm-1.2 hrs/no-
990 x 610 x 64 mm-1.6 hrs/no-
Brickwork Manhole
Task / DescriptionSlowAveFast
1.0 brick engineering-0.3 m²/hr - 3.23 ft²/hr-
1.5 brick engineering-0.2 m²/hr - 2.15 ft²/hr-
2.0 brick engineering-0.2 m²/hr - 2.15 ft²/hr-
build in pipes, under 150mm dia-0.1 hrs/no-
build in pipes, 150–225mm dia-0.2 hrs/no-
build in pipes, over 225mm dia-0.3 hrs/no-
build in cast iron covers0.3 hrs/no0.6 hrs/no1.2 hrs/no
Benching to Manholes
Task / DescriptionSlowAveFast
under 0.5m²-0.9 hrs/no-
0.5–0.75m²-1.2 hrs/no-
0.75–1.0m²-1.8 hrs/no-
Yard Gulleys
Task / DescriptionSlowAveFast
75–150mm dia pipes, bed and level-2.2 no/hr-
150–225mm dia pipes, bed and level-1.8 no/hr-
225–300mm dia pipes, bed and level-1.5 no/hr-
Road Gulleys
Task / DescriptionSlowAveFast
600mm deep, bed and level-1.2 no/hr-
750mm deep, bed and level-0.8 no/hr-
900mm deep, bed and level-0.4 no/hr-
1,200mm deep, bed and level-0.3 no/hr-
install gratings-5.0 no/hr-
PVC Manholes
Task / DescriptionSlowAveFast
PVC Manhole-15.0 mins/no-

Planning and Estimating Production Rates for Drainage Laying

PVC Drainage
Task / DescriptionSlowAveFast
1m pipes, 100–150mm dia, 0–5m run-5.7 m/hr - 18.70 ft/hr-
1m pipes, 100–150mm dia, 5–30m run-8.1 m/hr - 26.57 ft/hr-
1m pipes, 100–150mm dia, over 30m run-9.5 m/hr - 31.17 ft/hr-
3m pipes, 100–150mm dia, 0–5m run-12.2 m/hr - 40.03 ft/hr-
3m pipes, 100–150mm dia, 5–30m run-15.2 m/hr - 49.87 ft/hr-
3m pipes, 100–150mm dia, over 30m run-18.2 m/hr - 59.71 ft/hr-
6m pipes, 100–150mm dia, 0–5m run-22.2 m/hr - 72.83 ft/hr-
6m pipes, 100–150mm dia, 5–30m run-27.7 m/hr - 90.88 ft/hr-
6m pipes, 100–150mm dia, over 30m run-33.3 m/hr - 109.25 ft/hr-
3m pipes, 150–200mm dia, 5–30m run-10.6 m/hr - 34.78 ft/hr-
3m pipes, 150–200mm dia, over 30m run-12.8 m/hr - 41.99 ft/hr-
6m pipes, 150–200mm dia, 5–30m run-21.2 m/hr - 69.55 ft/hr-
6m pipes, 150–200mm dia, over 30m run-25.6 m/hr - 83.99 ft/hr-
Stoneware Drainage – Flexible Joints
Task / DescriptionSlowAveFast
75mm dia, over 30m run-12.5 m/hr - 41.01 ft/hr-
100mm dia, 0–5m run-7.7 m/hr - 25.26 ft/hr-
100mm dia, 5–30m run-9.1 m/hr - 29.86 ft/hr-
100mm dia, over 30m run-10.0 m/hr - 32.81 ft/hr-
150mm dia, 0–5m run-5.2 m/hr - 17.06 ft/hr-
150mm dia, 5–30m run-6.2 m/hr - 20.34 ft/hr-
150mm dia, over 30m run-7.7 m/hr - 25.26 ft/hr-
225mm dia, 0–5m run-2.7 m/hr - 8.86 ft/hr-
225mm dia, 5–30m run-3.3 m/hr - 10.83 ft/hr-
225mm dia, over 30m run-4.0 m/hr - 13.12 ft/hr-
300mm dia, 0–5m run-1.7 m/hr - 5.58 ft/hr-
300mm dia, 5–30m run-2.1 m/hr - 6.89 ft/hr-
300mm dia, over 30m run-2.5 m/hr - 8.20 ft/hr-
over 375mm dia, 0–5m run-1.4 m/hr - 4.59 ft/hr-
over 375mm dia, 5–30m run-1.6 m/hr - 5.25 ft/hr-
over 375mm dia, over 30m run-2.1 m/hr - 6.89 ft/hr-
PVC, Stoneware, Pitch Fibre & Concrete Joints
Task / DescriptionSlowAveFast
PVC, Stoneware, Pitch Fibre & Concrete Joints-2.4 mins/no-
Pitch Fibre Pipes
Task / DescriptionSlowAveFast
75mm dia, 0–5m run-9.1 m/hr - 29.86 ft/hr-
75mm dia, 5–30m run-16.6 m/hr - 54.46 ft/hr-
75mm dia, over 30m run-20.0 m/hr - 65.62 ft/hr-
100mm dia, 0–5m run-9.1 m/hr - 29.86 ft/hr-
100mm dia, 5–30m run-16.6 m/hr - 54.46 ft/hr-
100mm dia, over 30m run-20.0 m/hr - 65.62 ft/hr-
150mm dia, 0–5m run-6.6 m/hr - 21.65 ft/hr-
150mm dia, 5–30m run-12.5 m/hr - 41.01 ft/hr-
150mm dia, over 30m run-14.3 m/hr - 46.92 ft/hr-
200mm dia, 0–5m run-6.2 m/hr - 20.34 ft/hr-
200mm dia, 5–30m run-11.1 m/hr - 36.42 ft/hr-
200mm dia, over 30m run-12.5 m/hr - 41.01 ft/hr-
225mm dia, 0–5m run-5.8 m/hr - 19.03 ft/hr-
225mm dia, 5–30m run-10.0 m/hr - 32.81 ft/hr-
225mm dia, over 30m run-12.1 m/hr - 39.70 ft/hr-
Hepsleve Rubber Joint System
Task / DescriptionSlowAveFast
75mm dia, 0–5m run-12.5 m/hr - 41.01 ft/hr-
75mm dia, 5–30m run-14.3 m/hr - 46.92 ft/hr-
75mm dia, over 30m run11.2 m/hr - 36.75 ft/hr16.6 m/hr - 54.46 ft/hr30.1 m/hr - 98.75 ft/hr
100mm dia, 0–5m run-10.0 m/hr - 32.81 ft/hr-
Concrete Pipes
Task / DescriptionSlowAveFast
1.5m pipes, 525mm dia, 5–30m run-2.9 m/hr - 9.51 ft/hr-
1.5m pipes, 525mm dia, over 30m run-3.4 m/hr - 11.15 ft/hr-
1.5m pipes, 600mm dia, 0–5m run-2.4 m/hr - 7.87 ft/hr-
1.5m pipes, 600mm dia, 5–30m run-2.7 m/hr - 8.86 ft/hr-
1.5m pipes, 600mm dia, over 30m run-3.3 m/hr - 10.83 ft/hr-
1.5m pipes, 675mm dia, 0–5m run-2.2 m/hr - 7.22 ft/hr-
1.5m pipes, 675mm dia, 5–30m run-2.6 m/hr - 8.53 ft/hr-
1.5m pipes, 675mm dia, over 30m run-2.9 m/hr - 9.51 ft/hr-
1.5m pipes, 750mm dia, 0–5m run-1.1 m/hr - 3.61 ft/hr-
1.5m pipes, 750mm dia, 5–30m run-2.4 m/hr - 7.87 ft/hr-
1.5m pipes, 750mm dia, over 30m run-2.5 m/hr - 8.20 ft/hr-
1.5m pipes, 1,050mm dia-2.9 m/day - 9.51 ft/day4.2 m/day - 13.78 ft/day
1.5m pipes, 1,500mm dia-2.5 m/day - 8.20 ft/day3.8 m/day - 12.47 ft/day
1.5m pipes, 1,800mm dia-2.1 m/day - 6.89 ft/day2.6 m/day - 8.53 ft/day
2.5m pipes, 375mm dia, 0–5m run-3.6 m/hr - 11.81 ft/hr-
2.5m pipes, 375mm dia, 5–30m run-4.3 m/hr - 14.11 ft/hr-
2.5m pipes, 375mm dia, over 30m run-5.0 m/hr - 16.40 ft/hr8.0 m/hr - 26.25 ft/hr
2.5m pipes, 450mm dia, 0–5m run-3.4 m/hr - 11.15 ft/hr-
2.5m pipes, 450mm dia, 5–30m run-4.1 m/hr - 13.45 ft/hr-
2.5m pipes, 450mm dia, over 30m run-4.5 m/hr - 14.76 ft/hr9.0 m/hr - 29.53 ft/hr
2.5m pipes, 525mm dia, 0–5m run-3.3 m/hr - 10.83 ft/hr-
2.5m pipes, 525mm dia, 5–30m run-3.8 m/hr - 12.47 ft/hr-
2.5m pipes, 525mm dia, over 30m run-4.1 m/hr - 13.45 ft/hr-
2.5m pipes, 600mm dia, 0–5m run-3.0 m/hr - 9.84 ft/hr-
2.5m pipes, 600mm dia, 5–30m run-3.5 m/hr - 11.48 ft/hr-
2.5m pipes, 600mm dia, over 30m run-4.0 m/hr - 13.12 ft/hr-
2.5m pipes, 675mm dia, 0–5m run-2.8 m/hr - 9.19 ft/hr-
2.5m pipes, 675mm dia, 5–30m run-3.3 m/hr - 10.83 ft/hr-
2.5m pipes, 675mm dia, over 30m run-3.7 m/hr - 12.14 ft/hr-
2.5m pipes, 750mm dia, 0–5m run-2.6 m/hr - 8.53 ft/hr-
2.5m pipes, 750mm dia, 5–30m run-3.1 m/hr - 10.17 ft/hr-
2.5m pipes, 750mm dia, over 30m run-3.6 m/hr - 11.81 ft/hr-
Shingle Around Pipework
Task / DescriptionSlowAveFast
under 150mm dia-7.0 m/hr - 22.97 ft/hr-
over 150mm dia4.0 m/hr - 13.12 ft/hr5.5 m/hr - 18.04 ft/hr9.0 m/hr - 29.53 ft/hr

Planning and Estimating Man-hours for Manhole Cover Instillation

Manhole covers, including concrete filling
Light Duty
DescriptionTradesman HoursLabourer Hours
(450mm x 450mm - 18 in x 18 in)0.70 mhr/No - 0.70 mhr/No0.70 mhr/No - 0.70 mhr/No
(600mm x 600mm - 24 in x 24 in)0.85 mhr/No - 0.85 mhr/No0.85 mhr/No - 0.85 mhr/No
(900mm x 900mm - 36 in x 36 in)1.05 mhr/No - 1.05 mhr/No1.05 mhr/No - 1.05 mhr/No
Medium Duty
DescriptionTradesman HoursLabourer Hours
(450mm x 450mm - 18 in x 18 in)0.75 mhr/No - 0.75 mhr/No0.75 mhr/No - 0.75 mhr/No
(600mm x 600mm - 24 in x 24 in)0.95 mhr/No - 0.95 mhr/No0.95 mhr/No - 0.95 mhr/No
(900mm x 900mm - 36 in x 36 in)1.15 mhr/No - 1.15 mhr/No1.15 mhr/No - 1.15 mhr/No
Heavy Duty
DescriptionTradesman HoursLabourer Hours
(450mm x 450mm - 18 in x 18 in)0.80 mhr/No - 0.80 mhr/No0.80 mhr/No - 0.80 mhr/No
(600mm x 600mm - 24 in x 24 in)1.00 mhr/No - 1.00 mhr/No1.00 mhr/No - 1.00 mhr/No
(900mm x 900mm - 36 in x 36 in)1.20 mhr/No - 1.20 mhr/No1.20 mhr/No - 1.20 mhr/No
Trench grating, take delivery, build in frame and place in position
Light Duty
DescriptionTradesman HoursLabourer Hours
(225mm - 9 in wide)0.40 mhr/No - 0.40 mhr/No0.40 mhr/No - 0.40 mhr/No
(450mm - 18 in wide)0.65 mhr/No - 0.65 mhr/No0.65 mhr/No - 0.65 mhr/No
Heavy Duty
DescriptionTradesman HoursLabourer Hours
(225mm - 9 in wide)0.50 mhr/No - 0.50 mhr/No0.50 mhr/No - 0.50 mhr/No
(450mm - 18 in wide)0.80 mhr/No - 0.80 mhr/No0.80 mhr/No - 0.80 mhr/No