Production RatesExcavationExcavationExcavate and Remove

Excavate and Remove

Planning and Estimating Production Rates

Excavate Spoil Heaps to Transport
Task / DescriptionSlowAveFast
0.6m³ bucket – Sand / Soil14.5 m³/hr - 18.97 yd³/hr20.0 m³/hr - 26.16 yd³/hr25.6 m³/hr - 33.50 yd³/hr
0.6m³ bucket – Gravel Beds15.2 m³/hr - 19.90 yd³/hr20.4 m³/hr - 26.68 yd³/hr25.6 m³/hr - 33.50 yd³/hr
0.6m³ bucket – Clay / Chalk12.3 m³/hr - 16.09 yd³/hr18.5 m³/hr - 24.20 yd³/hr23.2 m³/hr - 30.34 yd³/hr
0.6m³ bucket – Boulder Clay11.2 m³/hr - 14.65 yd³/hr16.9 m³/hr - 22.11 yd³/hr21.3 m³/hr - 27.86 yd³/hr
1.1m³ bucket – Sand / Soil25.4 m³/hr - 33.22 yd³/hr30.3 m³/hr - 39.63 yd³/hr35.7 m³/hr - 46.70 yd³/hr
1.1m³ bucket – Gravel Beds25.6 m³/hr - 33.50 yd³/hr31.3 m³/hr - 40.94 yd³/hr37.0 m³/hr - 48.39 yd³/hr
1.1m³ bucket – Clay / Chalk22.5 m³/hr - 29.43 yd³/hr27.8 m³/hr - 36.36 yd³/hr33.3 m³/hr - 43.56 yd³/hr
1.1m³ bucket – Boulder Clay18.9 m³/hr - 24.72 yd³/hr24.4 m³/hr - 31.91 yd³/hr30.3 m³/hr - 39.63 yd³/hr
Load Spoil to Barge
CapacitySlowAveFast
2,000 m³-8.0 hrs - 8.0 hrs-
1,500 m³-6.5 hrs - 6.5 hrs-
1,000 m³-5.5 hrs - 5.5 hrs-
Spoil Conveyor
EquipmentSlowAveFast
600mm belt – 150m/min-260.0 m³/hr - 340.12 yd³/hr-