Production RatesExcavationExcavationEstimating Production Rates for Pneumatic Hammer Bulk Excavation

Estimating Production Rates for Pneumatic Hammer Bulk Excavation


* Production rates listed are based on 8-hr shift. The above figures are for general estimation purpose only and must not be used to guarantee any production figure to the customer. The actual working results may vary according to the quality and structure of the material to be broken, required degree of material size reduction, installation, condition of the carrier, conditions at the worksite, haulage of the broken material, skills of the operator etc.

Hammer (2,200lb – 1,000kg) – 315C Excavator
Task / DescriptionSlowAveFast
Non-Reinforced Concrete150 cu.yd - 115 m³200 cu.yd - 153 m³375 cu.yd - 287 m³
Reinforced Concrete140 cu.yd - 107 m³160 cu.yd - 122 m³240 cu.yd - 184 m³
Sedimentary Rock165 cu.yd - 126 m³200 cu.yd - 153 m³300 cu.yd - 229 m³
Volcanic Rock75 cu.yd - 57 m³110 cu.yd - 84 m³150 cu.yd - 115 m³
Hammer (3,740lb – 1,700kg) – 330C Excavator
Task / DescriptionSlowAveFast
Non-Reinforced Concrete275 cu.yd - 210 m³375 cu.yd - 287 m³490 cu.yd - 375 m³
Reinforced Concrete200 cu.yd - 153 m³150 cu.yd - 115 m³350 cu.yd - 268 m³
Sedimentary Rock250 cu.yd - 191 m³150 cu.yd - 115 m³400 cu.yd - 306 m³
Volcanic Rock135 cu.yd - 103 m³150 cu.yd - 115 m³275 cu.yd - 210 m³
Hammer (6,946lb – 3,150kg) – 345C Excavator
Task / DescriptionSlowAveFast
Reinforced Concrete300 cu.yd - 229 m³385 cu.yd - 295 m³850 cu.yd - 650 m³
Sedimentary Rock350 cu.yd - 268 m³440 cu.yd - 337 m³900 cu.yd - 688 m³
Volcanic Rock200 cu.yd - 153 m³275 cu.yd - 210 m³600 cu.yd - 459 m³