Dewatering

Planning and Estimating Production Rates

Task / DescriptionSlowAveFast
Setup small 2 hole system10.0 days - 10.0 days8.0 days - 8.0 days6.0 days - 6.0 days
Setup large 15 hole system-21.0 days - 21.0 days-
Calculate system times per pump-2.5 days/pump - 2.5 days/pump-
Setup Recharge System-3.5 days/pump - 3.5 days/pump-