Planning and Estimating Production Rates

Task / DescriptionSlowAveFast
Rule of Thumb, overall rate by Mill0.5 hrs/no1.1 hrs/no1.2 hrs/no
Fabricate reinforcement cages-4.0 hrs/cage-
Concreting barrette panels40.0 m³/hr - 52.32 yd³/hr50.0 m³/hr - 65.40 yd³/hr55.0 m³/hr - 71.93 yd³/hr
Trimming top of barrette panels-2.4 days/no-
Concrete Testing, Coring Test4.0 days/no3.5 days/no2.0 days/no
Concrete Testing, Sonic Logging Test-0.7 days/no-