Barrette Piles
Planning and Estimating Production Rates
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| Rule of Thumb, overall rate by Mill | 0.5 hrs/no | 1.1 hrs/no | 1.2 hrs/no |
| Fabricate reinforcement cages | - | 4.0 hrs/cage | - |
| Concreting barrette panels | 40.0 m³/hr - 52.32 yd³/hr | 50.0 m³/hr - 65.40 yd³/hr | 55.0 m³/hr - 71.93 yd³/hr |
| Trimming top of barrette panels | - | 2.4 days/no | - |
| Concrete Testing, Coring Test | 4.0 days/no | 3.5 days/no | 2.0 days/no |
| Concrete Testing, Sonic Logging Test | - | 0.7 days/no | - |