Planning and Estimating Production Rates

Task / DescriptionSlowAveFast
Concrete Pile Caps, 50-300mm deep and 0.6m dia0.6 hrs/no-0.3 hrs/no
Concrete Pile Caps, 300-750mm deep and 0.6m dia1.5 hrs/no-0.4 hrs/no
Concrete Pile Caps, > 750mm deep and 0.6m dia1.8 hrs/no-0.8 hrs/no
Concrete Pile Caps, 50-300mm deep and 1.1m dia1.9 hrs/no-0.8 hrs/no
Concrete Pile Caps, 300-750mm deep and 1.1m dia2.5 hrs/no-1.1 hrs/no
Concrete Pile Caps, > 750mm deep and 1.1m dia4.2 hrs/no-2.3 hrs/no
Concrete Pile Caps, 50-300mm deep and 2.5m dia9.2 hrs/no-8.2 hrs/no
Concrete Pile Caps, 300-750mm deep and 2.5m dia10.1 hrs/no-9.5 hrs/no
Concrete Pile Caps, > 750mm deep and 2.5m dia11.5 hrs/no-10.2 hrs/no
Concrete, Cutting Slabs, 5-25m deep-15.2 m/hr - 49.87 ft/hr-
Concrete, Cutting Slabs, 25-50m deep-11.5 m/hr - 37.73 ft/hr-
Concrete, Cutting Slabs, 50-75m deep-6.7 m/hr - 21.98 ft/hr-
Concrete, Cutting Holes, coring machine-0.2 m³/hr - 0.26 yd³/hr-
Concrete, Cutting Back to expose couplers 0.7m slab-2.5 m/day - 8.20 ft/day-