Power Supply
Planning and Estimating Production Rates
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| AC Install 2 no Service transformers, 6 men | - | 12.0 days | - |
| AC Install 2 no Switchgear, 7 men | - | 12.0 days | - |
| AC Install Associated Trays and ladders, 3 men | 11.0 days | 5.0 days | - |
| AC Cable Terminations in Tx and SWG Rooms, 3 men | 12.0 days | 6.0 days | - |
| DC Install Insulated Flooring in DC Room, 1 men | - | 5.0 days | - |
| DC Install 1 set Rectifier Transformer and Rectifier, 7 men | - | 1.0 days | - |
| DC Install Switchgear, 7 men | - | 10.0 days | - |
| DC Primary Cable Terminations and Busduct, 18 men | 12.0 days | 9.0 days | - |
| DC Secondary Cable Terminations and Connections, 9 men | 12.0 days | 6.0 days | - |
| Trackside Cabling 33kV/Pilot Cables, 10 men | 2,100.0 m run/day - 6,890.0 ft run/day | - | - |
| Trackside Cabling Terminations, 6 men | - | 1.0 days | - |