Production RatesMechanical ElectricalPower Supply

Power Supply

Planning and Estimating Production Rates

Task / DescriptionSlowAveFast
AC Install 2 no Service transformers, 6 men-12.0 days-
AC Install 2 no Switchgear, 7 men-12.0 days-
AC Install Associated Trays and ladders, 3 men11.0 days5.0 days-
AC Cable Terminations in Tx and SWG Rooms, 3 men12.0 days6.0 days-
DC Install Insulated Flooring in DC Room, 1 men-5.0 days-
DC Install 1 set Rectifier Transformer and Rectifier, 7 men-1.0 days-
DC Install Switchgear, 7 men-10.0 days-
DC Primary Cable Terminations and Busduct, 18 men12.0 days9.0 days-
DC Secondary Cable Terminations and Connections, 9 men12.0 days6.0 days-
Trackside Cabling 33kV/Pilot Cables, 10 men2,100.0 m run/day - 6,890.0 ft run/day--
Trackside Cabling Terminations, 6 men-1.0 days-