Fencing Works

Planning and Estimating Production Rates

Task / DescriptionSlowAveFast
Site Hoarding, timber posts, plywood nailed to horizontal rails1.0 m/hr - 3.28 ft/hr1.2 m/hr - 3.94 ft/hr-
Post Erection, Timber / Metal, dig, erect, fix3.3 no/hr4.5 no/hr-
Post Erection, Concrete, dig, erect, fix3.2 no/hr4.0 no/hr-
Fence Erection, Chainlink, posts at 1.5m-4.2 m/hr - 13.78 ft/hr-
Fence Erection, Chainlink, posts at 2.0m-4.4 m/hr - 14.44 ft/hr-
Fence Erection, Chainlink, posts at 3.0m-5.5 m/hr - 18.04 ft/hr-
Fence Erection, Chestnut Pailings, posts at 1.5m-23.8 m/hr - 78.08 ft/hr-
Fence Erection, Chestnut Pailings, posts at 2.0m-33.3 m/hr - 109.25 ft/hr-
Fence Erection, Chestnut Pailings, posts at 3.0m-41.6 m/hr - 136.48 ft/hr-
Fence Erection, Barbed Wire, posts at 1.5m-71.4 m/hr - 234.25 ft/hr-
Fence Erection, Barbed Wire, posts at 2.0m-100.0 m/hr - 328.08 ft/hr-
Fence Erection, Barbed Wire, posts at 3.0m-125.0 m/hr - 410.10 ft/hr-
Gate Erection, Chainlink on frame-4.1 no/hr-