Planning and Estimating Production Rates

Prep for Kerbs and Slabs

Task / DescriptionSlowAveFast
Concrete Road surfacing, Kerbs or Side Haunches-0.4 m³/hr - 0.52 yd³/hr-
Concrete Road surfacing, 150mm thick-12.5 m²/hr - 134.55 ft²/hr-
Concrete Road surfacing, 200mm thick-7.7 m²/hr - 82.88 ft²/hr-
Concrete Road surfacing, 300mm thick-6.7 m²/hr - 72.12 ft²/hr-

Kerb and Concrete Slab Production Rates

Task / DescriptionSlowAveFast
Concrete Slabs, laid on bedding, to slight falls2.7 m²/hr - 29.06 ft²/hr-4.2 m²/hr - 45.21 ft²/hr
Concrete Slabs, laid on bedding, to steep falls2.3 m²/hr - 24.76 ft²/hr-2.7 m²/hr - 29.06 ft²/hr
Concrete Slabs, laid in mortar, to slight falls1.5 m²/hr - 16.15 ft²/hr-2.3 m²/hr - 24.76 ft²/hr
Concrete Slabs, laid in mortar, to steep falls1.1 m²/hr - 11.84 ft²/hr-1.5 m²/hr - 16.15 ft²/hr
Concrete Slabs, laid on sand, to slight falls1.7 m²/hr - 18.30 ft²/hr-2.8 m²/hr - 30.14 ft²/hr
Concrete Slabs, laid on sand, to steep falls1.6 m²/hr - 17.22 ft²/hr-1.9 m²/hr - 20.45 ft²/hr
Cobble Stones, laid in mortar, no patterns-0.3 m²/hr - 3.23 ft²/hr-
Cobble Stones, laid in mortar, with patterns-0.2 m²/hr - 2.15 ft²/hr-
Artificial Stone, laid on sand, with patterns-2.5 m²/hr - 26.91 ft²/hr-
Brick Paviors, in mortar, straight joints0.9 m²/hr - 9.69 ft²/hr1.3 m²/hr - 13.99 ft²/hr1.9 m²/hr - 20.45 ft²/hr
Brick Paviors, in mortar, herringbone pattern-1.0 m²/hr - 10.76 ft²/hr1.2 m²/hr - 12.92 ft²/hr
Gravel Paths, including preparation of sub-base-10.5 m²/hr - 113.02 ft²/hr-
Concrete Paths, 100mm thick, including preparation of sub-base-2.5 m²/hr - 26.91 ft²/hr-
Concrete Kerbs or Channels, laid straight-6.2 m/hr - 20.34 ft/hr-
Concrete Kerbs or Channels, laid to 5m radius-4.5 m/hr - 14.76 ft/hr-
Concrete Kerbs or Channels, laid to 10m radius-5.0 m/hr - 16.41 ft/hr-
Concrete Kerbs or Channels, laid to 20m radius-5.5 m/hr - 18.05 ft/hr-
Stone/Granite Kerbs or Channels, laid straight-3.5 m/hr - 11.48 ft/hr-
Concrete Edging, laid straight-7.7 m/hr - 25.26 ft/hr-
Concrete Edging, laid to 5m radius-5.8 m/hr - 19.03 ft/hr-
Concrete Edging, laid to 10m radius-6.2 m/hr - 20.34 ft/hr-
Concrete Edging, laid to 20m radius-7.1 m/hr - 23.30 ft/hr-
Cutting and Fitting Ends, Concrete Kerbs-6.6 no/hr-
Cutting and Fitting Ends, Channels-5.8 no/hr-
Cutting and Fitting Ends, Concrete Edging-8.3 no/hr-