Rail Trackwork

Planning and Estimating Production Rates

Task / DescriptionSlowAveFast
FST Floating Track Slab, side restraints9.6 m/day - 31.50 ft/day--
FST Floating Track Slab, resin pads10.2 m/day - 33.46 ft/day--
FST Floating Track Slab, slab units10.6 m/day - 34.78 ft/day--
PCBT - Pre-cast Concrete Block Track, in Bored Tunnels17.1 m/day - 56.10 ft/day41.0 m/day - 134.51 ft/day-
PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels-35.0 m/day - 114.83 ft/day-
PCBT - Pre-cast Concrete Block Track, in Station Tunnels-35.0 m/day - 114.83 ft/day-
IST - Isolated Slab Track, in Bored Tunnels-20.0 m/day - 65.62 ft/day-
IST - Isolated Slab Track, in Cut and Cover Tunnels-34.0 m/day - 111.55 ft/day-
IST - Isolated Slab Track, in Station-29.0 m/day - 95.14 ft/day-
FST - Floating Slab Track, in Station3.6 m/day - 11.81 ft/day4.6 m/day - 15.09 ft/day5.7 m/day - 18.70 ft/day
Ballasted Track, in Mainline57.0 m/day - 187.01 ft/day71.0 m/day - 232.94 ft/day115.0 m/day - 377.30 ft/day
Ballasted Track, in Depot-28.0 m/day - 91.86 ft/day-
Non-Ballasted Track, in Depot8.5 m/day - 27.89 ft/day12.8 m/day - 41.99 ft/day17.4 m/day - 57.09 ft/day
Embedded / Paved Track, in Depot-71.0 m/day - 232.94 ft/day-
Heavy Maintenance / Train Wash Track, in Depot-29.0 m/day - 95.14 ft/day-
Maintenance Pit, in Depot-52.0 m/day - 170.60 ft/day-
Siding Trackwork, in Depot-38.0 m/day - 124.67 ft/day-