Subsoil Drains
Planning and Estimating Production Rates
Land Drains
Concrete, butt jointed
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| under 150mm dia, 0-5m run | - | 11.6 m/hr - 38.06 ft/hr | - |
| under 150mm dia, 5-30m run | - | 14.1 m/hr - 46.26 ft/hr | - |
| under 150mm dia, over 30m run | - | 18.8 m/hr - 61.68 ft/hr | - |
| 150-225mm dia, 0-5m run | - | 8.4 m/hr - 27.56 ft/hr | - |
| 150-225mm dia, 5-30m run | - | 10.2 m/hr - 33.46 ft/hr | - |
| 150-225mm dia, over 30m run | - | 11.9 m/hr - 39.04 ft/hr | - |
| 225-300mm dia, 0-5m run | - | 5.4 m/hr - 17.72 ft/hr | - |
| 225-300mm dia, 5-30m run | - | 6.5 m/hr - 21.33 ft/hr | - |
| 225-300mm dia, over 30m run | - | 7.9 m/hr - 25.92 ft/hr | - |